Hotels and tourism developments

Permits, licensing and classification

Last reviewed 25 October 2026

On this page

The stages

  1. Planning check — zoning, the 2026 Framework, protected areas, archaeological and forest restrictions.
  2. Environmental licensing — the category of the project determines whether an environmental impact assessment and approval, or standard environmental commitments, apply.
  3. Building permit — preliminary approval where required, then the permit; for a hotel, the specific building rules for tourist accommodation, parking and accessibility.
  4. Construction and completion — supervision, any revisions of the permit, the engineer’s completion certificates, utility connections.
  5. Operation — the notification of operation with its supporting documents (fire safety, health, the building’s legality) and the accommodation’s registry number.
  6. Classification — the star certificate, based on mandatory and optional criteria; a hotel that does not meet the category it advertises may be reclassified or suspended.

Where do hotel permits go wrong?

Revisions made on site without a revised permit; areas built beyond the permit that block the operating notification; an environmental approval that has lapsed before the permit is issued; a classification applied for at a category the building cannot reach. Each has a remedy — revision, legalisation where permitted, renewal, a reduced category — and each costs time in a seasonal business. The firm reviews the file at each stage so that the opening date is not lost at the last.

Frequently asked questions

Is the Special Operating Mark still required?

No. The Special Operating Mark is abolished for all accommodation covered by arts. 39 ff. of Law 4442/2016; references to it in older texts mean the notification of operation (art. 40(3)). Existing accommodation had to register by 31 December 2026.

Who decides the star category?

The Hellenic Chamber of Hotels certifies it on the basis of the MD 216/2015 criteria and an inspection.

Can we open part of the hotel while the rest is under construction?

Only where the completed part can lawfully operate on its own under the permit and the operating notification.

This page is general information and does not constitute legal advice. It reflects the law as at the date shown and may change.

Demetre E. Katsouris

Managing Partner, LL.B. LL.M. M.Sc.

Your person of contact

Speak to Demetre about Hotels and tourism developments

Tell us where you are and what you need. You will hear back from the lawyer who handles it, in English or in Greek.

Book a consultation